Key to code letters
Code letter | Above labourers' basic rate per week | Code letter | Above labourers' basic rate per week |
---|---|---|---|
A | £14.72 | H | £36.86 |
B | £16.20 | I | £44.23 |
C | £19.89 | J | £45.69 |
D | £28.00 | K | £49.41 |
E | £30.24 | L | £51.59 |
F | £31.67 | M | £53.81 |
G | £35.37 | N | £59.71 |
Last updated: August 2021
Building and Civil Engineering Craftsmen's Labourers
(to which Article 38(a) refers)
Extra payments for continuous extra skill or responsibility
With effect from 1 April 2016 the following extra payments will apply:
Labourer | Code letter |
---|---|
Timberman |
F |
Compressors |
B |
Concrete Mixers |
A |
Operative employed in and actually responsible for operating mixer over 10/7 but not including 21/14 capactiy (to apply to one operative per machine only) ... |
D |
Mechanical Drag Shovel: Operator of ... |
C |
Cranes, Hoists and Fork Lift Trucks |
F |
Banksmen appointed to attend crane and to be responsible for fastening or slinging loads and generally to direct crane driver... (This extra payment is not payable to a 'SIGNALMAN' appointed to act as such) |
D |
Power-driven crane or hoist up to and including 2 tons (2000kg) capacity: Driver of ... |
C |
Over 2 tons (2000kg) capacity: Driver of ... |
D |
Smooth-terrain fork-lift truck or side-loader; up to and including 3 tons (3000kg) capacity: Driver of ... |
C |
Over 3 tons (3000kg) capacity: Driver of ... |
D |
Rough-terrain fork-lift truck; up to and including 3 tons (3000kg) capacity: Driver of ... |
D |
Over 3 tons (3000kg) capacity: Driver of ... |
H |
Self-Propelled Mobile Crane on road wheels or caterpillar tracks; capacity over 30 cwts (1500kg) and up to and including 2 tons (2000kg): Driver of ... |
F |
Over 2 tons (2000kg) capacity: Driver of ... |
J |
Travelling or Climbing Tower Cranes; up to and including 2 tons (2000kg) capacity: Driver of ... |
F |
Over 2 tons (2000kg) and up to 5 tons (5000kg) capacity: Driver of ... |
J |
Over 5 tons (5000kg) capacity: Driver of ... |
M |
Derricks Power-driven derrick; up to and including 5 tons (5000kg) capacity: Driver of ... |
I |
Over 5 tons (5000kg) capacity: Driver of ... |
L |
Dumpers Dumper up to and including 2 tons (2000kg) capacity: Driver of ... |
C |
Over 2 tons (2000kg) and up to and including 7 tons (7000kg) capacity: Driver of ... |
F |
Over 7 tons (7000kg) capacity: Driver of ... |
K |
Excavators Excavator with rated capacity up to and including 3/8 cu.yd: Driver of ... |
D |
Over 3/8 cu.yd. up to and including 3/4 cu.yd. capacity: Driver of ... |
J |
Over 3/4 cu.yd. capacity: Driver of ... |
N |
Pumps Power-driven Pump: Attendant of ... |
A |
Road Rollers Hand Roller (power-driven): Operator of ... |
A |
Power-Roller: Under 4 tons (4000kg): Driver of ... |
C |
4 tons (4000kg) and over: Driver of ... |
F |
Tractors Calf-dozer: Driver of ... |
C |
Rubber-tyred tractor towing trailer: Driver of ... |
C |
Wheeled or tracked tractor (other than above) or shovel-loader up to and including 70hp: Driver of ... |
G |
Over 70hp: Driver of ... |
J |
Winches Power-driven Winch: Operator of ... |
E |
Mechanical Barrow Operator of ... |
A |
Elevators Mechanical Elevator: Operator of ... |
A |
Pipelayers and Jointers Pipes up to but not including 12in (300mm) diameter: Layer of ... |
C |
12in (300mm) diameter or over: Layer of ... |
D |
Pipe-jointer (stoneware or concrete pipes) ... |
C |
Trenching Machines Trenching Machine up to and including 30hp: Operator of.. |
D |
Over 30hp: Operator of ... |
J |
Concrete Workers Concrete leveller or vibrator operator ... |
A |
Concrete surface finisher (working off forms or other datum, eg road-form concrete haunch, edge beam or wire) ... |
C |
Note: The extra payments described above are not intended to apply to Concrete finishers required to use hand and/or power tools to provide a fine finish who normally receive the equivalent of the craft operatives' rate
Extra payments for intermittent responsibility
With effect from the 1 April 2021 the following extra payments will apply:
The extra payments set out below apply only during actual hours of employment and are not to be taken into account for the calculation of overtime and other premium payments.
While carrying out duties specified below, an operative shall receive, during the hours he is so engaged, the payments set out:
Operative duties | Extra per hour |
---|---|
Labourer, erecting, altering or dismantling simple access scaffolding with a working platform no higher than 5 metres | 24p per hour above Labourers' Rate |
Operatives other than craft operatives employed on dry-cleaning stone-work by mechanical process for the removal of protective material and/or discolouration (Employers to provide suitable masks) | 88p per hour above Labourers' Rate |
Building and Civil Engineering Craftsmen, Apprentices and Craftsmen's Labourers
(to which Article 37(b) refers)
Extra payments for work in discomfort and inconvenience
As part of the Single Craft Agreement and with effect from the 1 April 2002 the extra payments formerly paid under this Appendix will cease to be paid.